There are several factors and considerations that are taken into account when determining the need for a water main replacement. Replacement of existing water mains are evaluated and prioritized based on the age of the pipes, pipe materials, internal and external stresses, pipeline performance, and pipeline leaks & breaks. To assist with this task, the City utilizes a comprehensive risk-based computer model to evaluate these many factors and prioritize main replacements.  As water mains are replaced and as additional field data becomes available the City has an ongoing program to refine the model and generate updated recommendations. 

When feasible, replacement projects are scheduled with other City improvement projects, such as Public Works street, storm and sewer improvements, to minimize pavement replacement costs and disturbance to residents and businesses.

Below are projects currently under construction:


  • Rural Ridge Dr Main Replacement, estimated completion by Winter 2022
  • State College Main Replacement from Lincoln to La Palma, estimated completion by Fall 2020
  • Olive, Commercial and Patt Main Replacement, estimated completion by Spring 2021
  • Santa Ana Street Main Replacement between S Atchison St and S Vine St, estimated completion by Fall 2020
  • Tustin Ave railroad crossing pipe replacement, near LaPalma Ave, completion Summer 2021